PCD Engineering Division
1/17/2018 7:55:44 AM |
Reupload the Construction Plans and Final Drainage Report. The files are not displaying correctly. See attached screen capture. |
1/17/2018 7:55:44 AM |
PCD Project Manager
1/17/2018 7:49:51 AM |
Please upload the CD's and Drainage map in the drainage report. The line work is missing. | 1/17/2018 7:49:51 AM | |
PCD Engineering Division
1/3/2018 10:25:27 AM |
No additional comments. | 1/3/2018 10:25:27 AM | |
View |
EPC County Attorney's Office
12/27/2017 12:10:15 PM |
12/27/2017 12:10:15 PM | |
View |
EPC County Attorney's Office
12/21/2017 1:02:31 PM |
12/21/2017 1:02:31 PM | |
View |
PCD Project Manager
12/12/2017 8:15:51 AM |
Multi-discipline letter review 2 | 12/12/2017 8:15:51 AM |
View |
PCD Project Manager
12/12/2017 8:10:11 AM |
Plat version 2 red lines | 12/12/2017 8:10:11 AM |
View |
PCD Project Manager
12/12/2017 8:09:40 AM |
Drainage report redlines version 2 | 12/12/2017 8:09:40 AM |
PCD Engineering Division
12/11/2017 11:52:16 AM |
Review 2 redline comments on the following documents will be uploaded by the Project Manager: - Drainage Report Comments resolved for the following: - Construction Drawings - Financial Assurance Estimate - GEC - Plat - TIS |
12/11/2017 11:52:16 AM | |
View |
EPC Health Department
12/4/2017 3:23:34 PM |
12/4/2017 3:23:34 PM | |
Pikes Peak Regional Building Department
12/4/2017 2:11:55 PM |
NO FURTHER COMMENTS. | 12/4/2017 2:11:55 PM | |
View |
EPC Parks Department
12/1/2017 3:38:27 PM |
El Paso County Community Services/Parks Final Comments | 12/1/2017 3:38:27 PM |
View |
EPC Environmental Services
11/30/2017 3:08:26 PM |
11/30/2017 3:08:26 PM | |
Mountain View Electric Association, Inc.
11/28/2017 2:20:08 PM |
Thank you for the utility easements shown on the plat of Filing #3 and Filing #4. See comments from June 8, 2017 if additional information is needed or contract MVEA. |
11/28/2017 2:20:08 PM | |
US Postal Service
11/22/2017 2:47:36 PM |
This development is in Monument. Please contact the Postmaster for Monument - ruth.r.phsigoda@usps.gov | 11/22/2017 2:47:36 PM | |
911 Authority - El Paso/Teller County
11/21/2017 2:21:34 PM |
No comment for 911. All street names previously approved Thank you Justin |
11/21/2017 2:21:34 PM | |
Colorado Division of Water Resources
11/20/2017 1:29:53 PM |
The water supply plan does not appear to have changed, therefore please see our prior letter dated June 20, 2017 for our comment. | 11/20/2017 1:29:53 PM | |
Mountain View Electric Association, Inc.
8/15/2017 1:00:30 PM |
Two of the documents under the Project Name of Jackson Ranch, Filing #3 Plat are for Hannah Ridge at Feathergrass. Please sent to Final Plat and Letter of Intent that apply to Jackson Ranch for review. Thank you, MVEA |
8/15/2017 1:00:30 PM | |
Colorado Division of Water Resources
8/15/2017 6:17:12 AM |
From the submitted information the water supply plan has not changed, therefore please see our letter dated June 20, 2017 for our comments. | 8/15/2017 6:17:12 AM | |
View |
EPC Parks Department
7/27/2017 9:40:06 AM |
El Paso County Community Services/Parks Final Comments | 7/27/2017 9:40:06 AM |
View |
Tri-Lakes-Monument Fire Protection District
7/7/2017 8:15:06 AM |
Comments are attached, JCB | 7/7/2017 8:15:06 AM |
View |
EPC Health Department
6/26/2017 6:47:34 PM |
6/26/2017 6:47:34 PM | |
View |
PCD Project Manager
6/26/2017 11:03:19 AM |
Multi-disciplinary team letter | 6/26/2017 11:03:19 AM |
View |
PCD Project Manager
6/26/2017 10:48:52 AM |
Traffic Memo Redlines | 6/26/2017 10:48:52 AM |
View |
PCD Project Manager
6/26/2017 10:48:30 AM |
SWMP Redlines | 6/26/2017 10:48:30 AM |
View |
PCD Project Manager
6/26/2017 10:48:01 AM |
Grading and Erosion Control Plan Redlines | 6/26/2017 10:48:01 AM |
View |
PCD Project Manager
6/26/2017 10:47:26 AM |
Construction Drawings Redlines | 6/26/2017 10:47:26 AM |
View |
PCD Project Manager
6/26/2017 10:46:48 AM |
EGF Redlines | 6/26/2017 10:46:48 AM |
View |
PCD Project Manager
6/26/2017 10:46:27 AM |
Drainage Report Redlines | 6/26/2017 10:46:27 AM |
View |
PCD Project Manager
6/26/2017 10:45:56 AM |
Plat redlines. Engineering is in blue and Planning is in green. | 6/26/2017 10:45:56 AM |
Pikes Peak Regional Building Department
6/23/2017 1:03:30 PM |
Standard Final Plat comments: 1. Enumerations/Floodplain will review the mylar prior to plat for address placement, street naming, title block and floodplain statement. 2. $10.00 per lot and tract fee will be due at the time of the review of the mylar. If an address is not needed on a tract then no fee applies. Check should be made out to Regional Building Department. Paid directly to the Enumerations department. 3. A copy of the final recorded plat is required prior to plan submittal. |
6/23/2017 1:03:30 PM | |
911 Authority - El Paso/Teller County
6/21/2017 9:09:38 AM |
No action for 911 All street names previously approved Justin |
6/21/2017 9:09:38 AM | |
View |
EPC Parks Department
6/20/2017 3:48:41 PM |
El Paso County Community Services/Parks Preliminary Comments (Please Reopen for Final Comments) | 6/20/2017 3:48:41 PM |
View |
Colorado Division of Water Resources
6/20/2017 7:12:21 AM |
6/20/2017 7:12:21 AM | |
View |
EPC Environmental Services
6/16/2017 2:01:21 PM |
6/16/2017 2:01:21 PM | |
PCD Engineering Division
6/13/2017 11:45:42 AM |
Engineering redline comments on the following pdf documents will be uploaded by the project managers: Construction Drawings, Final Drainage Report, Final Plat, Financial Assurance Estimates, Grading and Erosion Control, and Traffic Impact Study. | 6/13/2017 11:45:42 AM | |
View |
PCD Engineering Division
6/13/2017 11:31:21 AM |
Attached is the SWMP Checklist identifying items that needs to be addressed. Include the checklist with the resubmittal noting the page number where the missing items are addressed. |
6/13/2017 11:31:21 AM |
View |
Mountain View Electric Association, Inc.
6/8/2017 2:36:53 PM |
6/8/2017 2:36:53 PM | |
Upper Black Squirrel Creek GWMD
6/7/2017 1:01:37 PM |
The Board of Director's of the Upper Black Squirrel Creek GWMD does not have any comments at this time. Please send any future submittals. | 6/7/2017 1:01:37 PM | |
EPC County Attorney's Office
6/5/2017 4:07:36 PM |
Water review will be drafted upon receipt of State Engineer's letter. Edi Anderson |