View: Project Documents
Agency | Comment | ||
---|---|---|---|
View |
PCD Project Manager
9/28/2017 9:23:12 AM |
MTD letter review 4 | 9/28/2017 9:23:12 AM |
View |
PCD Project Manager
9/18/2017 4:56:05 PM |
Review 3 Grading and Erosion Control Plan red lines. Please correct, sign and upload for County Engineer approval | 9/18/2017 4:56:05 PM |
View |
PCD Project Manager
9/18/2017 4:55:17 PM |
Drainage report review 3 red lines, Please correct, sign and upload for County Engineer approval stamp. | 9/18/2017 4:55:17 PM |
View |
PCD Project Manager
9/18/2017 4:52:17 PM |
Cd's 3rd review red lines. Please correct and upload signed CD's | 9/18/2017 4:52:17 PM |
View |
PCD Project Manager
9/18/2017 4:48:51 PM |
Review 3 MTD letter | 9/18/2017 4:48:51 PM |
PCD Engineering Division
9/18/2017 3:14:16 PM |
See comment letter and minor redlines. | 9/18/2017 3:14:16 PM | |
View |
EPC Health Department
9/7/2017 10:28:05 AM |
9/7/2017 10:28:05 AM | |
View |
Colorado Division of Water Resources
8/31/2017 1:07:48 PM |
8/31/2017 1:07:48 PM | |
View |
PCD Project Manager
8/29/2017 4:14:02 PM |
Review 2 Multi-discipline letter | 8/29/2017 4:14:02 PM |
View |
PCD Project Manager
8/29/2017 4:06:49 PM |
Traffic review 2 red lines | 8/29/2017 4:06:49 PM |
View |
PCD Project Manager
8/29/2017 4:06:14 PM |
SWMP review 2 red lines | 8/29/2017 4:06:14 PM |
View |
PCD Project Manager
8/29/2017 4:05:51 PM |
Plat review 2 red lines | 8/29/2017 4:05:51 PM |
View |
PCD Project Manager
8/29/2017 4:05:22 PM |
grading & erosion Control Plan review 2 red lines | 8/29/2017 4:05:22 PM |
View |
PCD Project Manager
8/29/2017 4:04:41 PM |
EGF review 2 redlines | 8/29/2017 4:04:41 PM |
View |
PCD Project Manager
8/29/2017 4:04:21 PM |
Drainage Report Review 2 red lines | 8/29/2017 4:04:21 PM |
View |
PCD Project Manager
8/29/2017 4:03:38 PM |
CD's review 2 redlines | 8/29/2017 4:03:38 PM |
PCD Engineering Division
8/29/2017 3:51:06 PM |
See comment review letter and electronic redlines. | 8/29/2017 3:51:06 PM | |
View |
EPC Parks Department
8/29/2017 10:03:01 AM |
El Paso County Community Services / Parks Final Comments (No PAB Action Needed) | 8/29/2017 10:03:01 AM |
Pikes Peak Regional Building Department
8/28/2017 1:15:05 PM |
No further comments | 8/28/2017 1:15:05 PM | |
Colorado Springs Airport Advisory Commission
8/24/2017 8:00:37 AM |
The Airport has no additional comments for the second review of this project. | 8/24/2017 8:00:37 AM | |
Cimarron Hills Fire
8/22/2017 8:16:03 PM |
No Additional Comments at this time. | 8/22/2017 8:16:03 PM | |
Colorado Springs Utilities, Dev, Svc.(includes water resources)
8/17/2017 4:02:37 PM |
Kari, CSU has reviewed the final plat for Hannah Ridge Filing No 3. All comments have been addressed and approval is recommended. Let me know if you need anything further. Thanks, Ryne |
8/17/2017 4:02:37 PM | |
Mountain View Electric Association, Inc.
8/16/2017 10:35:45 AM |
Thank you for the opportunity to review Hannah Ridge #3 with the new comments. Cathy Hansen-Lee Mountain View Electric Assoc. |
8/16/2017 10:35:45 AM | |
911 Authority - El Paso/Teller County
8/15/2017 11:13:51 AM |
No action for 911 All street names previously approved Thanks Justin |
8/15/2017 11:13:51 AM | |
Cherokee Metro Dist
6/27/2017 3:31:58 PM |
This development is within the Cherokee Metropolitan District service boundary. The applicant has been notified of the development process that they will need to go through. --- Jonathon Smith | 6/27/2017 3:31:58 PM | |
View |
EPC County Attorney's Office
6/26/2017 3:31:59 PM |
6/26/2017 3:31:59 PM | |
View |
EPC Parks Department
6/16/2017 9:14:45 AM |
El Paso County Community Services/Parks Final Comments | 6/16/2017 9:14:45 AM |
View |
PCD Project Manager
6/14/2017 3:26:18 PM |
Water Resources Report Redlines | 6/14/2017 3:26:18 PM |
View |
PCD Project Manager
6/14/2017 3:22:58 PM |
The wastewater report should be updated. Please see redlines | 6/14/2017 3:22:58 PM |
View |
PCD Project Manager
6/14/2017 3:22:00 PM |
Traffic Study Redlines | 6/14/2017 3:22:00 PM |
View |
PCD Project Manager
6/14/2017 3:21:10 PM |
The recorded maintenance agreement may need to be revised. Please see comments on uploaded document. | 6/14/2017 3:21:10 PM |
View |
PCD Project Manager
6/14/2017 3:20:24 PM |
Plat Redlines | 6/14/2017 3:20:24 PM |
View |
PCD Project Manager
6/14/2017 3:19:50 PM |
Overlot Grading Construction Drawing Redlines | 6/14/2017 3:19:50 PM |
View |
PCD Project Manager
6/14/2017 3:18:42 PM |
Letter of Intent-Please see redlines | 6/14/2017 3:18:42 PM |
View |
PCD Project Manager
6/14/2017 3:17:36 PM |
Fire Commitment- Verify taxing entity | 6/14/2017 3:17:36 PM |
View |
PCD Project Manager
6/14/2017 3:16:58 PM |
ESQCP Redlines | 6/14/2017 3:16:58 PM |
View |
PCD Project Manager
6/14/2017 3:16:26 PM |
Drainage Report Redlines | 6/14/2017 3:16:26 PM |
View |
PCD Project Manager
6/14/2017 3:15:52 PM |
Closure sheet | 6/14/2017 3:15:52 PM |
View |
PCD Project Manager
6/14/2017 3:15:28 PM |
Cherokee Commitment Letter | 6/14/2017 3:15:28 PM |
View |
PCD Project Manager
6/14/2017 3:14:41 PM |
Construction Drawing Redlines | 6/14/2017 3:14:41 PM |
View |
PCD Project Manager
6/14/2017 3:14:06 PM |
By laws. Please verify that these are not changing. Please add reception number to plat note. | 6/14/2017 3:14:06 PM |
View |
PCD Project Manager
6/14/2017 3:27:32 PM |
Please see red lines on individual submittal items. Please note, all recorded documents should be reflected within the plat notes with the document name, purpose, and reception number. | 6/14/2017 3:27:32 PM |
View |
Colorado Division of Water Resources
6/1/2017 12:25:13 PM |
6/1/2017 12:25:13 PM | |
Pikes Peak Regional Building Department
5/31/2017 9:10:48 AM |
Will the tracts require addressing? Standard FP comments: 1. Enumerations/Floodplain will review the mylar prior to plat for address placement, street naming, title block and floodplain statement. 2. $10.00 per lot and tract fee will be due at the time of the review of the mylar. If an address is not needed on a tract then no fee applies. Check should be made out to Regional Building Department. 3. A copy of the final recorded plat is required prior to plan submittal. |
5/31/2017 9:10:48 AM | |
View |
EPC Health Department
5/30/2017 3:44:26 PM |
5/30/2017 3:44:26 PM | |
View |
EPC Parks Department
5/30/2017 11:21:24 AM |
El Paso County Community Services/Parks Preliminary Comments (Please Reopen for Final Comments) | 5/30/2017 11:21:24 AM |
View |
Colorado Springs Utilities, Dev, Svc.(includes water resources)
5/25/2017 3:47:20 PM |
5/25/2017 3:47:20 PM | |
911 Authority - El Paso/Teller County
5/25/2017 9:06:32 AM |
Hello, No action is needed for 911. All road names have been previously reserved for this project. Thanks, Connie |
5/25/2017 9:06:32 AM | |
View |
Colorado Springs Airport Advisory Commission
5/24/2017 4:50:13 PM |
5/24/2017 4:50:13 PM | |
Mountain Metro Transit (City of COS)
5/17/2017 3:26:41 PM |
This project has no effect to the Mountain Metro system. We have no comments. Thank you | 5/17/2017 3:26:41 PM | |
View |
Mountain View Electric Association, Inc.
5/15/2017 11:11:26 AM |
5/15/2017 11:11:26 AM | |
Cimarron Hills Fire
5/11/2017 10:40:04 AM |
CHFD reviewed, commitment letter on file. | 5/11/2017 10:40:04 AM | |
EPC County Attorney's Office
5/10/2017 2:14:58 PM |
Water review will be completed upon receipt of State Engineer's findings. Edi Anderson |
5/10/2017 2:14:58 PM |