View: Project Documents
Agency | Comment | ||
---|---|---|---|
View |
PCD Engineering Division
5/10/2017 7:49:43 AM |
Remove the standalone Grading and Erosion Control standard signature blocks on sheet 1 since site grading is less than 1 acre. | 5/10/2017 7:49:43 AM |
View |
Colorado Springs Utilities, Dev, Svc.(includes water resources)
4/24/2017 3:18:06 PM |
Raimere, No comment. CSU recommends approval. Thanks, Joe Noble, P.E. Project Engineer Colorado Springs Utilities 719-668-3683 jnoble@csu.org |
4/24/2017 3:18:06 PM |
View |
Colorado Springs Airport Advisory Commission
4/24/2017 9:00:41 AM |
4/24/2017 9:00:41 AM | |
Pikes Peak Regional Building Department
4/24/2017 8:39:10 AM |
Not sure why this request was placed for review, the plan was approved and permit has been pulled? Plan C96119 & Permit K90769 | 4/24/2017 8:39:10 AM | |
PCD Engineering Division
4/18/2017 5:05:53 PM |
Site Plan review comments: 1. Remove the linework and labels for future improvements. 2. Include a viewport showing the entire property boundary. The viewport must show the relative location of the flow control station and the proposed gravel driveway to the building. 3. The included Legal Description/Exclusive Utility Easement does not show an access easement to the utility easement. Is there a separate document that allows access through the property. Show the access easement on the site plan. Landscape Plan comments: 1. Remove the future improvements and show the proposed gravel driveway. |