Description
This purpose of this request is to dedicate to El Paso County a 60' ROW for Myers Road as it exists through Section 3 and the East Half of Section 4, Township 17 South, Range 61 West of the 6th P.M., County of El Paso, State of Colorado
Location
Parcels
1700000021 1700000021 1700000023 1700000023 1700000024 1700000024
Applicant
Marr Land Surveying
Thomas Marr ( tmarr@marrlandsurveying.com )
(719) 660-8623
Thomas Marr ( tmarr@marrlandsurveying.com )
(719) 660-8623
File Number
ROW241
Project Manager
Kari Parsons
Status
Closed
Created
1/24/2024 1:19:35 PM

View: Project Documents



Review Comments (8)

Link Agency Comment
County Attorney - Development Review
4/24/2024 1:37:21 PM
County Attorney's Office will schedule the ROW acceptance before the BoCC for the May 7 agenda. We will provide a tax proration for 2024 taxes that have accrued to that date, which must be paid prior to the hearing. 4/24/2024 1:37:21 PM
PCD Project Manager
4/22/2024 10:46:46 AM
Please work directly with County Attorney's office, Lori Seago or Apriil Willie (719-726-0512) to schedule this before the Board of County Commissioners. 4/22/2024 10:46:46 AM
PCD Engineering Division
4/22/2024 10:34:20 AM
No comments from development services engineering.

reviewed by:
Daniel Torres
danieltorres@elpasoco.com
4/22/2024 10:34:20 AM
County Attorney - Development Review
3/19/2024 11:24:12 AM
1. Please confirm with the County planner whether a subdivision exemption is needed for creation of this tract.
2. Please provide an updated title commitment specific to this proposed tract to identify any possible conflicts with existing easements or other interests.
3. If 2023 taxes have not yet been paid on the larger parcels this year, they must be paid before the BoCC hearing. County Attorney's Office will also request a tax proration from the Treasurer's Office for any taxes that have accrued on the ROW tracts in 2024; those taxes must also be paid before the BoCC hearing.
4. The County Attorney's Office can then schedule this matter before the BoCC for approval.
3/19/2024 11:24:12 AM
PCD Engineering Division
3/5/2024 10:36:10 PM
No comments from development services engineering.

reviewed by:
Daniel Torres
danieltorres@elpasoco.com
3/5/2024 10:36:10 PM
EPC Stormwater Review
3/4/2024 2:38:40 PM
Review 1: EPC DPW Stormwater has no comments. Planner: no re-review necessary.

Reviewed by:
Mikayla Hartford
Stormwater Engineer I
MikaylaHartford@elpasoco.com
3/4/2024 2:38:40 PM
PCD Engineering Inspections
2/26/2024 7:13:28 AM
Inspections has no commits 2/26/2024 7:13:28 AM
EPC Parks Department
2/22/2024 1:26:29 PM
El Paso County Parks and Community Services Department, Review Comments: The ROW deeding of this section of Myers Road to El Paso County does not impact any existing or proposed parks, trails, or open space. The proposed Hanover Road Bicycle Route is located along Myers Road, but remains in the ROW as an on-road facility, and as such, no trail easements are necessary. 2/22/2024 1:26:29 PM